Project Updates

(as of August 11, 2025)

    • The site is now fully mobilized

    • Unit work in the following buildings has been completed: 321 Monmouth, 329 Monmouth, 80 Brunswick, 191 Wayne, 82-86 Brunswick (with the exception of 1 unit due to exigent circumstances)

    • Select unit work, All Shingle Roofs, Soffits/Fascia, Gutter/Leaders, Windows

    • 45 units have been completed and signed off

    • Which buildings are currently under renovation? 33-43 Brunswick, 34-44 Brunswick, 375 Montgomery St

    • Additional ongoing work items include: Unit Work, Site Work started, Façade work, Boiler work

    • Which buildings will be completed? 33-43 Brunswick, 34-44 Brunswick, and 375 Montgomery St will be completed. 361 Montgomery will be started

    • Which scope items will be completed? Unit Work, Flat Roofs, Windows at Midrise Buildings

    • How many units will be started? Approximately 20 units

    • How many units will be completed? Select units at 361 Montgomery