Project Updates
(as of August 11, 2025)
-
The site is now fully mobilized
Unit work in the following buildings has been completed: 321 Monmouth, 329 Monmouth, 80 Brunswick, 191 Wayne, 82-86 Brunswick (with the exception of 1 unit due to exigent circumstances)
Select unit work, All Shingle Roofs, Soffits/Fascia, Gutter/Leaders, Windows
45 units have been completed and signed off
-
Which buildings are currently under renovation? 33-43 Brunswick, 34-44 Brunswick, 375 Montgomery St
Additional ongoing work items include: Unit Work, Site Work started, Façade work, Boiler work
-
Which buildings will be completed? 33-43 Brunswick, 34-44 Brunswick, and 375 Montgomery St will be completed. 361 Montgomery will be started
Which scope items will be completed? Unit Work, Flat Roofs, Windows at Midrise Buildings
How many units will be started? Approximately 20 units
How many units will be completed? Select units at 361 Montgomery